activities

Here you will find our different dissemination activities as well as access to  public deliverables developed throughout the project.

news

work packages

Interact activities are structured into following seven work packages:

    • WP1 is the Project Management and WP7 contains all dissemination activities.
    • In WP2 successful PED approaches will be analysed, a competence network for the INTERACT regions established, and success factors of best practice described.
    • In WP3 the current status of the INTERACT regions will be documented, a gap analysis to the required infrastructure done, and the future design of the LINK architecture established.
    • In WP4 the technical design of the energy community including interfaces between stakeholders and use-cases will be developed, and the LINK-based market designed.
    • In WP5 the legal framework, business models, economic evaluations and potential contracting models will be established.
    • All generated knowledge will be tuned to the special requirements of the INTERACT regions and integrated into a specific Roadmap for each energy community within WP6.
activities - work packages

Interact activities are structured into following seven work packages:

  • WP1 is the Project Management and WP7 contains all dissemination activities.
  • In WP2 successful PED approaches will be analysed, a competence network for the INTERACT regions established, and success factors of best practice described.
  • In WP3 the current status of the INTERACT regions will be documented, a gap analysis to the required infrastructure done, and the future design of the LINK architecture established.
  • In WP4 the technical design of the energy community including interfaces between stakeholders and use-cases will be developed, and the LINK-based market designed.
  • In WP5 the legal framework, business models, economic evaluations and potential contracting models will be established.
  • All generated knowledge will be tuned to the special requirements of the INTERACT regions and integrated into a specific Roadmap for each energy community within WP6.
activities - work packages

deliverables

Del. no. Deliverable name WP no. Delivery date Download
D1.1 INTERACT First Year Activity Reporting 1 M14
D1.2 INTERACT Second Year Activity Reporting 1 M24
D2.1 Competence Map 2 M6
D2.2 Stakeholder Needs Evaluation 2 M7
D2.3 Key success factors and requirements for INTERACT energy communities 2 M10
D3.1 Common Inventory Methodology for recording current technologies 3 M5
D3.2 Gap analysis including the list and description of existing technologies and infrastructure as well as necessary replacements/upgrades/additions to the infrastructure and measuring devices 3 M15
D3.3 LINK-ICT structure with communication guidelines between the actors within the electricity community 3 M18
D4.1 Design of the Energy Community Organisation according to the LINK-Solution 4 M12
D4.2 Use Cases for the integration of the existing innovative technologies with the LINK-solution 4 M17
D4.3 Market structure and its interfaces with the Energy Community 4 M19
D5.1 Current legal framework and differences between the PED-Call target countries 5 M15
D5.2 Business cases for the INTERACT energy community 5 M18
D5.3 Required contracting models and economic evaluation of the solution 5 M21
D6.1 Roadmap for the implementation of the designed INTERACT energy community in general and for the specific local perspectives 6 M24
D7.1 Dissemination implementation plan / First version M2 and updates every 6 month after 7 M2
– Academic papers 7 M3
D7.2 Project Website 7 M4
D7.3 Materials made for design workshops, website and social media including (content, illustrations, banners, animations and infographics for complex information), with ongoing updates and additions 7 M3-24
– Poster 7
– Flyer 7
– Video 7
– Newsletter 7
– Academic papers 7
D7.4 Final Dissemination report and Info-Flyer about the established Roadmap 7 M24
– Flyer 7